Council approves change order for Fire Station gear dryer; mayor raises liquidated‑damages concern

City of Missouri Valley City Council · February 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved change order PCO-006-2 for a gear dryer in the fire apparatus bay and the mayor noted the Fire Station Addition project is roughly 120 days past completion and suggested pursuing liquidated damages; no formal damages action was taken.

The Missouri Valley City Council approved change order PCO-006-2 to install a gear dryer in the Fire Station apparatus bay during its Feb. 24 special meeting. The motion to approve the change order was made by Councilmember Struble and seconded by Councilmember Tuttle; roll call votes were recorded as ayes by those present.

Separately, Mayor Roger Marshall raised for the council’s attention that the Fire Station Addition project is approximately 120 days past its scheduled completion and suggested the council consider pursuing liquidated damages. The comment was recorded as a request for council awareness; no formal motion or vote to assess liquidated damages was taken during the meeting. Councilmember Gilpin earlier asked about the punch list for the fire bay, and William Huey said he was waiting on an individual named Rogge to provide outstanding documents needed for project closeout.