Board approves change order, roundabout payment and registers claims totaling about $280,409
Summary
The commission approved change order number 9 for the Colorado tracking project (directional boring to a junction box), authorized a $253,350 roundabout payment, approved requisitions for lease-rental bonds, and accepted the register of claims (total shown in packet: $280,409.46). Staff said the larger projects remain under budget overall.
Get email alerts on the Finance Payments topic
No spam. Unsubscribe anytime.
The Hobart Redevelopment Commission on March 16 approved multiple project payments and financial items, including a construction change order, a roundabout payment, requisitions tied to lease-rental bonds and the register of claims.
Project staff (speaker 3) described change order number 9 for the Colorado tracking project as work to connect electrical service to a junction box after a NIPSCO pole relocation required directional boring. The presenter said the project remains approximately $64,000 under budget and recommended payment of the change order to allow the contractor to continue work. The amount for change order number 9 was stated orally in the meeting but recorded in the packet as an item to be paid; the transcript rendering of the amount was unclear. The board moved and approved the change order.
The board also approved payment application #1 for the roundabout project in the amount of $253,350 after staff reported most major work is complete though minor items remain. The payment motion was moved, seconded and approved by voice vote.
Staff presented requisitions related to lease-rental bond projects and requested approval of bond requisition numbers 76 and 77; the board approved those requisitions individually. The register of claims presented for consideration listed a total of $280,409.46; the board voted to approve the register of claims by voice vote.
Commissioners noted they lacked a maintenance funding mechanism for future landscaped roundabout elements and asked staff to keep plantings minimal to avoid shifting maintenance to the parks department. No dissenting roll-call votes were recorded in the meeting transcript.