Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the 38th Place Improvements topic

No spam. Unsubscribe anytime.

Board approves bidding for 38th Place phases 1–2 and reissues County Line culvert bid

Hobart City Redevelopment Authority · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board authorized issuing plans and bids for Phases 1 and 2 of the 38th Place/Fillmore project (estimated ~ $5.3M with 15% contingency for phases 1–2) and voted to reissue bid documents for the County Line culvert concurrently.

The Authority approved moving forward with advertising and bidding for Phases 1 and 2 of the 38th Place/Fillmore improvement project and reissuing bid documents for the County Line culvert project to run concurrently.

Staff said Phase 1 and 2 are currently estimated at about $5.3 million including a 15% contingency; the bond had anticipated up to $6 million. A pre-bid conference was scheduled and staff described an April advertising schedule with a May bid opening and award at the board’s May meeting. DNR permits for an outfall at Stacey Creek were reported as approved, pending right-of-entry from affected property owners.

The board also authorized reissuing County Line culvert bid documents and noted that the County Line project will have a shorter bid window and that the road cannot be closed for more than 14 days during the work. Staff said they plan concurrent procurement to improve pricing and schedule efficiency.

Next steps: staff to publish ads, hold pre-bid conference, and return with bids for board award according to the presented schedule.