Middlefield committee approves $484,044 in payments and change orders for firehouse project

Middlefield Public Safety and Firehouse Building Committee ยท January 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

On Jan. 7, 2026 the Middlefield Public Safety and Firehouse Building Committee approved payments totaling $395,875.10 and three change orders totaling $88,169.62 for the town's firehouse construction project; the largest single payment was $387,948.80 to PDS (invoice #6).

Paul Pizzo, chairman of the Middlefield Public Safety and Firehouse Building Committee, called the Jan. 7, 2026 meeting to order at 7:00 p.m. and the committee approved a slate of payments and three change orders for the town's firehouse construction project.

The committee voted to approve payments totaling $395,875.10, including $387,948.80 to PDS (invoice #6, Dec. 31, 2025), $5,983.80 to Arcadis (invoice #36096077, Jan. 6, 2026), $1,685.00 to Testcon (invoice #13268, Dec. 23, 2025), $192.50 for two months of administrative services, and $65.00 to Landmark Architects for two self-inking stamps. All payment motions were moved, seconded, and recorded as "Motion Carried." The committee also approved three construction change orders totaling $88,169.62: change order #4 for ledge blasting ($51,537.75), change order #5 for a concealed fastener panel ($32,503.65), and change order #6 for screen wall engineering ($4,128.22). Each change order motion carried.

Why it matters: these approvals move committed project funding into active payables and authorize contract changes that affect construction scope and cost. The committee received a schedule and construction-status packet from the design/build team and the owner's representative and addressed questions by item and page number; the packet indicated items completed, in progress and upcoming. Committee members noted no new funding sources or grant awards at the meeting.

Attendance: Present were Paul Pizzo (Chairman), Bruce Villwock, Pete Tyc, Ryan Colwell, Kevin Boyle, Ross Burton and Steven Tyc; Alice Malcolm was recorded absent. Minutes for Nov. 5 and Dec. 3, 2025 were approved earlier in the meeting.

Key payments and motions approved: - PDS: $387,948.80 (invoice #6, Dec. 31, 2025). Motion by Bruce Villwock, second by Kevin Boyle; motion carried. - Arcadis: $5,983.80 (invoice #36096077, Jan. 6, 2026). Motion by Ryan Colwell, second by Kevin Boyle; motion carried. - Testcon: $1,685.00 (invoice #13268, Dec. 23, 2025). Motion by Steven Tyc, second by Bruce Villwock; motion carried. - Administrative services (Amity): $192.50 for Nov.-Dec.; motion by Bruce Villwock, second by Kevin Boyle; motion carried. - Landmark Architects: $65.00 (invoice #0824 for two stamps). Motion by Kevin Boyle, second by Bruce Villwock; motion carried.

Approved change orders: - Change order #4 (ledge blasting): $51,537.75. Motion by Steven Tyc, second by Ross Burton; motion carried. - Change order #5 (concealed fastener panel): $32,503.65. Motion by Steven Tyc, second by Bruce Villwock; motion carried. - Change order #6 (screen wall engineering): $4,128.22. Motion by Paul Pizzo, second by Kevin Boyle; motion carried.

The committee adjourned at 8:33 p.m. The meeting packet, including the schedule and payables list, was provided by the design/build team and the owner's representative. Meeting minutes were signed and "Respectfully submitted" by Amity French-Wilson.

Next steps: project schedule and status will continue to be tracked by the design/build team and owners' representative; no new grant awards or directives were reported at this meeting.