County seeks approval for $5,470 change order to replace smoke detectors at juvenile facility

Cowlitz County Board of Commissioners · June 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works requested board approval for a $5,470 change order after a contractor discovered nonfunctioning smoke detectors during fire-panel replacement at a 24-hour juvenile facility; the work was not included in the original bid because the detectors were not verifiable until the panel was operational.

Cowlitz County Public Works notified commissioners that a replacement fire panel at a county juvenile facility revealed several nonfunctioning smoke detectors and that the contractor—Point Monitor—proposed a $5,470 change order to replace those detectors.

"We are asking for board approval on that today for the $5,470 change order," Mike Moss, Public Services Director, said, explaining that the smoke detectors were discovered only after the replacement panel was tested and that the amount represents roughly 10% of the original bid. Moss said the county solicited three bids for the overall project and followed purchasing processes.

Commissioners discussed the county's change‑order policy and practices; staff said historically the board requires approval of change orders that are 10% or more of the contract price to control escalating contractor costs. No formal vote was recorded on the change order during the meeting.