Council approves $290,910.94 payment request for city hall/police renovation; completion timeline slides

Charles City Council · August 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved payment request No. 6 (Resolution 8725) for $290,910.94 to contractor Kingland for mechanical and demolition work on the city hall/police renovation; staff said substantial completion slipped from late March to early May and the contract contains no liquidated damages.

The Charles City Council approved Resolution 8725 at its meeting to process payment request No. 6 to contractor Kingland for the city hall–police department renovation project, in the amount of $290,910.94.

City staff member John said the payment covers mainly mechanical work—HVAC, heating, ventilation and air-conditioning—and associated demolition. With this disbursement, staff said the city will have paid Kingland a little over $1.2 million across six payment requests.

John told the council the project schedule has slipped: the original substantial-completion target had been late March, but the contractor’s latest schedule indicates substantial completion in early May. He attributed some delay to a required additional wall and change orders that extended the timeline.

Councilmembers asked whether the contract includes liquidated damages for schedule overrun; John said the architect and contractor did not include liquidated damages typical for some building projects and that the contract contains no such penalties.

A councilmember moved and seconded approval of the resolution; the motion was recorded and the clerk called the roll. Staff said final completion work will include punch-list items and paperwork after substantial completion is reached.

The council discussed no additional contractual remedies at the meeting; the resolution was approved as presented.