Pella staff outline $10 million in projects, options for memorial building and timeline for community center decision
Summary
Staff presented updates on three capital projects totaling about $10 million — the memorial building, 215 Main Street, and an $8.3 million community center — and sought council input ahead of December financial decisions; council debated selling or repurposing the memorial building and reviewed cost uncertainties for elevator replacement at 215 Main Street.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City staff briefed the Pella City Council on three capital projects in the current fiscal-year budget with an approximate combined cost of $10 million: renovation of the memorial building (2115 Main Street), activation of 215 Main Street for Planning & Zoning and other offices, and an $8.3 million community center plan.
On the memorial building, staff noted a 10-year user agreement with the American Legion, about 160 annual rentals, roof and foundation issues, and a $300,000 budget placeholder tied to earlier 2021 estimates; council debated whether the city should sell, repurpose or preserve the historic structure and stressed accessibility concerns if veterans were to move to another site.
Staff proposed moving Planning & Zoning and the driver’s license station to 215 Main Street, using the main floor and reserving upper floors for future needs; the elevator could require replacement at an estimated $1.0–$1.5 million, a primary cost-driver, and staff reported recent basement water intrusion that has been addressed.
For the community center, staff described programming that would house Community Services, an art center and expanded city programming along with continued presence by local performing groups. Staff said December will be the decision point for financing and final project scope and asked council for input ahead of further engineering and formal approvals.
Public commenters and a representative from the Friends group noted the value of a certified kitchen for vendor use and community programming. Council asked staff to continue refining costs, address accessibility needs and return with formal engineering estimates before final votes.