St. James Township accepts KM Contractors' $89,000 bid for Marina North Project, amends Marina Fund

St. James Township Board · April 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board accepted a single bid from KM Contractors for the Marina North Project at $89,000 and approved amending the Marina Fund capital outlay to $95,000 during the April 16 special meeting.

The St. James Township Board on April 16 opened the Marina North Project bidding documents and received one bid. Trustee Peirano moved, and Trustee Cole supported, a motion to accept KM Contractors as the lowest bidder at $89,000; the motion passed on a roll-call vote with Cole, McDonough, Peirano and Welke voting yes.

Following award of the bid, the board approved a motion by Trustee Cole, supported by Trustee Peirano, to amend the Marina Fund capital outlay amount to $95,000; that motion also passed on a unanimous roll-call vote.

Why it matters: accepting the bid and increasing capital outlay authorizes the township to proceed with the Marina North Project under the contract amount recorded in the minutes and commits additional Marina Fund resources. The minutes do not detail construction schedule, contract terms, or funding sources beyond the fund name.

Next steps: the board accepted the bid and amended the budget; contract execution and project scheduling were not specified in the minutes.