Dobson Drain culvert work will close a lane on M‑13 through summer, council hears
Summary
Standish staff told the council the Dobson Drain box‑culvert project at US‑23/M‑13 will run from late May to mid‑October and require one lane closure on M‑13 for the summer; the culvert is 169 feet long and utilities cross the site.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Standish City Council was briefed Feb. 10 on the schedule for the Dobson Drain box‑culvert project at US‑23/M‑13 at Mill Street, which staff said will start at the end of May, run through mid‑October and result in a one‑lane closure on M‑13 for the summer.
Staff described the culvert as 169 feet long and said utilities run along the culvert alignment, creating coordination needs during construction. Council members were advised the project timeline will affect traffic flow along M‑13 for the summer construction season.
No motions or permit decisions were made at the Feb. 10 meeting; the item was presented as an informational update to the council.