Board hears broad facilities update; approves committee reappointments and software renewal, accepts first reading of device and e‑bike policies

Wiseburn Unified School District Board of Education · June 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported progress on Delair athletic and playground work, classroom flooring and ceiling replacements, Weisburn Middle exterior painting, access control and ADA upgrades; the board reappointed Measure EE oversight committee members and approved a bond‑program software renewal 4–0, and accepted a first reading of device/ebike policy language.

A substantial portion of the meeting focused on facilities projects and routine board actions tied to bond and safety work.

Facilities director Mr. Mayberry provided project‑by‑project updates: netting work and synthetic turf removal are underway at Delair soccer field, with contractors aiming for substantial use of the field by mid‑August and final completion by Sept. 19; Delair’s playground replacement and safety‑pad replacement began in mid‑June with an early‑August target for use and September final completion; a multi‑phase Delair classroom refresh is replacing ceiling tiles and flooring (luxury vinyl plank and carpet) with sequencing designed to enable staged re‑occupation of classrooms. Staff also described plans to remove rust and repaint lunch shelters with marine‑grade coatings, and they reviewed the ongoing exterior painting program at Weisburn Middle School using a concrete‑adhesion primer and marine‑grade top coats to withstand coastal air.

Mayberry said door access control wiring and ADA work are scheduled next week at Delair and Holly Glenn and that Da Vinci’s cafe project is complete and operational. The district previewed a feasibility study and an RFP for a future Delair TK building expansion planned for 2027 and invited board members to a Measure EE citizen oversight tour on Aug. 3.

The board took several routine actions: it reappointed Measure EE citizens bond oversight committee members (11.1) and approved a fiscal‑year 2026–27 software services renewal with KBY Technologies to support the Measure EE bond program (11.2); both motions carried 4–0. The board also received a first reading on updated policies addressing electronic devices (including watches) and e‑bike classifications (noting the district’s approach aligns with state/city classifications that limit high‑speed class‑3 e‑bikes on campus).

Why it matters: The bond‑funded projects affect school safety, access and athletics; the oversight committee and software renewal are governance and fiscal controls for Measure EE implementation. Policy changes about devices and e‑bikes could affect daily campus management and student conduct rules.

The board adjourned after routine business.