Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
NMHS roof work underway; gym floor nearly complete; Sarah Noble oil tank removed
Summary
Mayor Pete Bass reported roofing crews began work and completed eight panels; Mayor Bass estimated about 40% of the roof still needs attention. Dr. Janet Parlato said the NMHS gym floor is roughly 80% complete. The board noted the Sarah Noble oil tank was removed.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Board members received updates on facilities across the district at the July 16 meeting.
Mayor Pete Bass told the board that roofing contractors began work the day before and had "completed eight panels today." He estimated that roughly 40% of the roof requires attention. Mr. Tom O'Brien said he reviewed the plan at the MBC meeting and was impressed with it; Mayor Bass said Mr. Cunningham and Mr. Manka were consulted and are being updated daily.
Dr. Janet Parlato reported the New Milford High School gym floor is about 80% complete. Mr. O'Brien also reported that the oil tank at Sarah Noble Intermediate School has been removed.
The updates were informational; the board did not take separate action beyond receiving the reports.
