Stamford board approves plans to bid auditorium roof replacement at Newfield Elementary

Stamford Board of Education ยท January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a 6:30 p.m. special meeting the Stamford Board of Education certified final plans and authorized bidding for a roof replacement at Newfield Elementary School; the board voted unanimously to move the $350,000 project forward, expecting about 60% state reimbursement.

The Stamford Board of Education voted unanimously at a 6:30 p.m. special meeting to certify final plans and authorize bidding for a roof replacement over the auditorium at Newfield Elementary School.

Chair Haiden moved to approve Resolution 01-14-25:01, which asks the board to certify review of final plans and project manuals for State Project No. 135-0284 dated 11/07/2024; the motion was seconded and passed by voice/hand vote with all members in favor.

Presenter Catherine Labobo told the board the work covers about 7,000 square feet and targets a failing section of roof that has exceeded its useful life. "It's a small roof over the auditorium that has come up on the end of its life," Labobo said, noting the district submitted a roughly 140-page bid package to state reviewers.

Labobo said the project budget is $350,000 and the district expects about 60% reimbursement from the state โ€” roughly $210,000. She described the planned cover as EPDM, a rubberized roofing product warrantied for 20 years and commonly eligible for state reimbursement; the bid includes an option for an additional 10-year warranty if costs allow. "So we're going to see if we can do that within our $350,000 total project budget," Labobo said.

Dr. Hammond, who said he had recently visited the site, voiced support for the work and noted its importance to teachers in that wing. Board members asked clarifying questions about the standard reimbursement rate and the expected warranty life; Labobo said the district has been successful in getting close to the full 60% and that while longer-life roofing could be pursued, the state would reimburse only for the 20-year portion.

After the vote, Chair Haiden directed Melissa Lovall to proceed with the project to keep it on schedule for the summer. No amendments or opposing votes were recorded during the meeting.

The special meeting was then adjourned; the chair noted a separate TLC meeting would follow, where a master staffing plan by Amy Baldotti and staff would be discussed.