Commission approves restructured funding to build Otay Mesa East northbound vehicle facilities

California Transportation Commission · June 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The CTC approved program and allocation actions that reprioritize construction of northbound vehicle and tolling facilities at the Otay Mesa East port of entry, allowing toll revenues to begin earlier and support future bond sales for remaining components, per staff recommendation.

The California Transportation Commission approved a set of program amendments and a multifunded allocation linked to the Otay Mesa East port of entry project, restructuring the delivery so northbound vehicle facilities and tolling infrastructure are built first to allow earlier revenue generation.

Beverly, presenting tabs 100–103 and Tab 104, said the proposal follows discussion with the San Diego Association of Governments and CALTRANS and is intended to improve the project's financing by enabling early tolling and supporting bond sales. The staff recommendation included returning certain funds to the program associated with scope changes on another Port of Oakland project and memorializing prior scope amendments.

Vice Chair and other commissioners emphasized the project's regional economic consequences and the importance of advancing the northbound facilities. Commissioner Falcone noted the corridor's significant trade volume and jobs supported by cross‑border commerce.

The commission voted to approve the program amendments and the multifunded allocation for the Otay Mesa East northbound vehicle processing and tolling package. Commissioners voiced unanimous support by voice vote; the transcript records the motion and second and the chair's remarks endorsing the decision.

What happens next: staff will process the allocation and baseline agreement amendments so construction of the prioritized northbound facilities and tolling systems can proceed.

Attribution: reporting is based on the presenters and commissioners quoted during the relevant agenda items in the meeting transcript.