Dollar General final plans cleared by Summit Soil & Water; village engineer to sign cover sheet
Summary
Engineer Rich Wasosky reported that Summit Soil & Water approved the Dollar General final plans and the design engineer delivered corrected plans to the Village Service Department; the village engineer will review and sign the cover sheet so the developer can obtain a zoning certificate.
Get email alerts on the Development topic
No spam. Unsubscribe anytime.
The Village of Northfield engineer told council on Feb. 12 that Summit Soil & Water has approved final site plans for a proposed Dollar General store and that the design engineer delivered an updated, corrected set of plans to the Village Service Department.
Engineer Rich Wasosky said he plans to review the final set and sign the cover sheet, a procedural step that will allow the developer to apply for and receive the village zoning certificate. No hearing or council vote on the zoning certificate was recorded at the meeting; Mr. Wasosky’s action is the remaining administrative step noted in the transcript.
Council did not record a timetable for construction or additional conditions in the minutes; the village will proceed with standard zoning‑certificate and permitting processes once the cover sheet is signed.