Casey approves pay estimate and loan draws for Water Main Improvement Project; accepts SRF forgiveness
Summary
The council accepted an estimated $291,000 SRF loan forgiveness, approved pay estimate #5 for Max Smith Construction LLC as presented, and authorized CDBG and SRF draw requests to fund recent project work.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
At the June 2 meeting, the Casey City Council advanced payments and funding for the Water Main Improvement Project following an update from Jordan Kappos of Veenstra & Kimm Inc.
Kappos reported that water lines and services are in place and contractors were finishing seeding and road repairs. He presented pay estimate #5 for Max Smith Construction LLC and informed the council of an estimated State Revolving Fund (SRF) loan forgiveness amount of $291,000.
The council voted to accept the SRF loan forgiveness agreement (motion by Rick Richter, second by Bret Wedemeyer; all ayes) and approved pay estimate #5 for Max Smith Construction LLC (motion by Bret Wedemeyer, second by Theresa Schiller; all ayes). The minutes record the pay estimate presented in Kappos’s update as $136,873.12.
Separately in the meeting record, the consent/claims listing includes an entry for Max Smith Construction LLC described as "Wtr Main Proj Draw #5" for $78,315.28 in the claims list. The minutes therefore show both a claims listing entry and a project pay estimate in different parts of the document; the council's formal approval at the project presentation was to the pay estimate as presented by the consultant.
Council also approved a Community Development Block Grant (CDBG) Water Main Project GAX #6 draw request for $83,356.00 (motion by Theresa Schiller, second by Bret Wedemeyer; all ayes) and an SRF loan distribution request claim draw #6 for $57,651.42 (motion by Rick Richter, second by Bret Wedemeyer; all ayes).
The approved draws and pay estimates fund contractor payments and project closeout activities; the council recorded acceptance of SRF forgiveness to reduce the community's loan obligation for the project.