Sarkanno: Water treatment project moving forward but engineering invoice needs more detail

Daggett County Municipal Building Authority · October 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Sarkanno reported the water treatment plant project is progressing and said an engineering invoice was received but requires additional detail before she can submit it for reimbursement.

Sarkanno provided the Municipal Building Authority with an update on the county's water treatment plant project, saying the effort is "continuing moving forward." She told the authority she had received an invoice from the engineering company but asked the engineer to return and provide additional details before she could submit the invoice for reimbursement.

"We did receive an invoice from the engineering company, but I needed him to go back in and provide some other details before I can submit it for reimbursement," Sarkanno said, adding she had discussed the needed changes that morning.

No change orders or formal budget actions tied to the water treatment project were presented at the meeting.