Public commenter urges no exterior stairways as SHA readies Feb. 24 RFP review for 705 redevelopment
Summary
At the Sudbury Housing Authority meeting, a resident reiterated objections to the 705 redevelopment and asked that future plans presented at a Feb. 24 RFP review show no exterior stairways; SHA staff said a meeting with CHA will review a draft design-build RFP and consider alternatives to previously paused designs.
Get email alerts on the 705 Redevelopment topic
No spam. Unsubscribe anytime.
Chair S. Swanger opened the Sudbury Housing Authority meeting on Feb. 10, 2026. During public comment, Alicia Carillo of 68 Basswood Ave. repeated her objections to the proposed 705 redevelopment project and said she expects any plans presented at a Feb. 24 meeting to show no exterior stairways.
Executive Director S. Cusolito told the board the authority will meet with the Massachusetts Housing Authority (CHA) on Feb. 24 to review a draft request for proposals for design-build services related to the 705 redevelopment. She said she will not attend but recommended the board proceed given scheduling constraints among commissioners. Cusolito added that work by the firm ZED is on hold and that the RFP review is an opportunity to consider other design types that might be more cost-effective.
Why it matters: the RFP review and CHA meeting will shape the design and procurement approach for the 705 site; public concerns about building features such as exterior stairs could shape community input the board receives before selecting a design-build approach.
Board members did not take a formal vote on the redevelopment at the Feb. 10 meeting. The next procedural step is the Feb. 24 meeting with CHA to review the draft RFP. The board also continues outreach and recruitment activities as it prepares for future engagement on redevelopment options.