Region 4 building committee approves payments, OKs two change orders for John Winthrop Middle School security project

Region 4 Board of Education John Winthrop Security Project Building Committee · October 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a remote Oct. 16 meeting, the Region 4 Building Committee received a construction update on the John Winthrop Middle School security addition, approved consultant invoices and a $179,146 contractor payment application, and approved two change orders totaling $7,156.19 while asking the architect to seek a lower price on a proposed as-built survey.

The Region 4 Building Committee for the John Winthrop Middle School security project met remotely on Oct. 16, 2025, and voted to approve consultant invoices, a contractor payment application and two contractor change orders while discussing an as-built survey price that the committee asked the architect to negotiate down.

The committee’s action came after a construction progress report from QA+M Architecture. Erin Benken, QA+M, and architect Rusty Malik told the committee that exterior site work — including seeding, planting, planter boxes and mulching — is complete; concrete and asphalt site work, ADA sidewalks, ramps and grading are finished; canopy framing has passed inspection; lighting and railings are installed; and interior drywall work is underway. Mr. Malik reported the elevator installation is scheduled for Nov. 10 if the vendor’s crews are available; local inspections by the Building Official and Fire Marshal are expected in mid-December, and the state elevator inspection will be scheduled after installation.

Finance consultant Robert Grissom gave a brief budget update, saying the only payments since last month were $9,201.80 to CT Comp for camera hardware and use of contingency for previously approved change orders. He reported a construction contingency balance of $38,969.93.

On motions made and seconded (names of mover and seconder are not specified in the meeting record), the committee unanimously approved QA+M invoice #17403 for $6,920.40 and QA+M invoice #17476 for $3,066.60 for construction administration services for August and September, respectively. The committee also unanimously approved Orlando Annulli & Sons Payment Application #5 in the amount of $179,146.00 for work completed through September, with the architect confirming that a fully signed version of the application will be obtained from the contractor.

The committee reviewed Orlando Annulli & Sons Change Order Proposal #13Rev2 (Survey As-Built) for $3,675.00. Mr. Malik reported that the contractor’s price appeared to be roughly $1,000 higher than a competing vendor’s quote of $2,500. The committee requested that the architect attempt to secure a counter-proposal from the contractor that would match the lower amount; the change order was not approved pending the contractor’s response.

Two proposed change orders were approved. The committee unanimously approved Change Order Proposal #16 (additional grading and paving of 336 square feet at the traffic circle) dated Oct. 10, 2025, for $6,114.02, noting the work was required by the Building Official. The committee also unanimously approved Change Order Proposal #17 (relocate a fire alarm horn and strobe in the upper elevator lobby per the Fire Marshal’s direction) dated Oct. 10, 2025, for $1,042.17.

Committee members also flagged two potential future costs for awareness: rewiring lighting in the canopy and stairwells within secured vestibule areas to balance code/security needs and energy/cost concerns, and finalizing the cost to run elevator electrical conduit into the elevator shaft (the committee previously authorized a Not-To-Exceed amount of $3,000 for that work; final costs remain pending).

There was no public comment. Chairman Rick Daniels adjourned the meeting at 9:05 a.m.

What’s next: The architect will follow up with the contractor on the as-built survey pricing and provide an updated proposal; the elevator installation and subsequent inspections remain scheduled as noted, and further change-order discussions will return to the committee when additional pricing or contractor responses are available.