Willington committee sets steps toward Oct. 6 referendum, starts appraisals and Phase I environmental review of River Road site

Willington School Building Committee · June 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee agreed on a target October 6 referendum date, outlined September public hearings and a town meeting to set the referendum, and started due diligence on a River Road parcel (appraisals requested, Phase I site environmental assessment underway) while town and seller attorneys draft a purchase-and-sale agreement.

The Willington School Building Committee on June 8 moved forward on schedule and site work tied to a school project referendum.

Scott, the committee’s project lead, presented a milestone schedule that targets a town referendum on Tuesday, Oct. 6, 2026, with a Board of Selectmen public hearing around Sept. 8, a second public hearing near Sept. 15, and a town meeting on Sept. 22 when the specific referendum would be set. Scott said the town would enter a roughly two-week blackout period about two weeks before the referendum.

On site due diligence, Scott and Mike described a recent site walk of a River Road parcel. The committee has issued a request for appraisal services with responses anticipated by the end of the week; Scott said Phase I site environmental assessment work is under way and the design team is assessing geotechnical and septic locations. Scott said the Phase I report is expected around June 22.

Mike told the committee that town and seller attorneys are exchanging drafts of a purchase-and-sale agreement, with an initial draft expected this week. He emphasized the P&S is likely to be staged — an early due-diligence phase followed by a more extended negotiation that will support grant applications and the public process.

Committee members asked staff to ensure due-diligence costs would be eligible for reimbursement if the town approves the project later; staff confirmed some pre-approval costs would be reimbursable under grant rules if the project proceeds and the town purchases the property after the referendum.

What’s next: appraisals and the Phase I environmental report, and continued coordination of the draft purchase-and-sale agreement; staff will update the committee as documents and reports arrive.