Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Solar topic
No spam. Unsubscribe anytime.
Sterling P&Z raises decommissioning and bonding concerns over proposed Brookfield Husky solar field
Summary
The Sterling Planning & Zoning Commission discussed a notification the town received for a Brookfield Husky Solar project, noted the Connecticut Siting Council has jurisdiction, and flagged questions about ownership, panel abandonment, and reclamation bonds; the application was filed 2/20/26 with a decision due 8/19/26.
Get email alerts on the Solar topic
No spam. Unsubscribe anytime.
The Sterling Planning & Zoning Commission discussed a notification from Pullman & Comley on behalf of Brookfield Husky Solar, LLC about a proposed solar field and raised questions about decommissioning, long-term ownership and reclamation bonding.
The Commission learned the solar application was filed on Feb. 20, 2026, and that the Connecticut Siting Council — not the local P&Z — holds permitting authority. “The P&Z Commission has received the notification letter from Pullman & Comley on behalf of Brookfield Husky Solar, LLC,” Chair Jason McLevy said. Selectman Pattie Massey asked whether the commission could prevent the proposal; Consulting Planner Jim Larkin said the Siting Council has jurisdiction and that the Town may be able to petition for a public hearing. Larkin noted a decision is due Aug. 19, 2026.
Why it matters: commissioners expressed practical concerns that are commonly raised with utility-scale solar: short-term ownership structures, the risk that panels could age out or be abandoned, and whether an appropriate reclamation bond or decommissioning plan will be required. Those details affect local taxpayer exposure and long-term site maintenance.
What was said and next steps: Massey asked whether P&Z had authority to stop the project; after a general discussion the commission concluded more research is necessary. Larkin advised the Connecticut Siting Council has total jurisdiction, but he said the Town might be able to petition for a public hearing. The commission did not adopt a formal motion on the project at the meeting and directed staff to gather more information on Town rights, bonding options, and the Siting Council process.
The application filing date (Feb. 20, 2026) and the Siting Council decision deadline (Aug. 19, 2026) were recorded by staff; the commission recommended reviewing statutory and regulatory options and monitoring the Siting Council docket for opportunities to comment or petition for a hearing.