Votes at a glance: Corydon council approves tax abatement, two sewer change orders and several routine items

City of Corydon City Council · October 23, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its Oct. 23 meeting the Corydon City Council approved Resolution 2025-021 (tax abatement for 544 E. State), two sewer change orders totaling $15,575.45, accepted a low bid for a maintenance shed, authorized quotes for East Lagoon decommissioning, and took other routine actions; a truck sale received no bids.

The Corydon City Council took several mostly routine actions at its Oct. 23 meeting, approving a tax abatement, two change orders on a sewer relining project, and awarding a shed bid while taking no action on a municipal truck sale.

Key actions and outcomes

- Resolution 2025-021 (tax abatement for 544 E. State Street, Brian Draper): Approved. Motion by Kyle Hampton; second by Kenny Holmes. Vote: Clark, Hampton, Holmes, Wolfe — Ayes; Nays: none.

- Change Order #4 (sewer relining/repair): Approved. Motion by Kenny Holmes; second by Bryan Wolfe. Amount: $11,625.45. Rationale: a different size liner was required for a portion of the sewer line.

- Change Order #5 (sewer relining/repair): Approved. Motion by Bryan Wolfe; second by Chase Clark. Amount: $3,950.00. Rationale: an internal spot repair was required after a portion of line collapsed during lining.

- Bid for sale of 2007 Chevy truck with snowplow: No bids received; no action taken. Jared Chambers said he will list the truck and plow on an auction site.

- Maintenance shed at south lagoon: Low bid accepted from Central Iowa Sheds in the amount of $3,359.16 if purchased by Nov. 30, 2024. Motion by Chase Clark; second by Kenny Holmes. Approved unanimously.

- Authorization to request quotes for decommissioning the East Lagoon: Authorized by motion of Chase Clark; second by Kyle Hampton. The motion directs staff to solicit quotes for sludge judging and sample testing as an initial step.

- Approval of consent agenda (unpaid/prepaid bills, Oct. 9 minutes with Clark’s correction, alcohol renewal for Shanks Farms/Bowling Green Lanes): Approved. Motion by Chase Clark; second by Kyle Hampton.

Most votes were unanimous among the four councilors present (Chase Clark, Kyle Hampton, Kenny Holmes and Bryan Wolfe). Several items required follow-up work (quotes, auction listing, and a council work session for a traffic study).