Board approves Pleasant Grove Road paving contract; county engineer outlines schedule and liquidated damages
Summary
Supervisors approved a roughly 1.2-mile paving contract for Pleasant Grove Road after County Engineer Brian Carter described the bidding process, a June 1 start date, 70 working days, and $1,000/day liquidated damages for delay.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Des Moines County Board approved a pavement contract for Pleasant Grove Road, covering the stretch from Highway 61 to Iowa City Road and including the Iowa City Road intersection.
County Engineer Brian Carter told supervisors the project — just under 1.2 miles — drew six bidders; he characterized the low bid as favorable compared with the county’s estimate. He told the board the contract allows a June 1 start, anticipates 70 working days to completion, and includes liquidated damages of $1,000 per working day for late performance. Carter also said the county will aim to complete work before harvest to minimize disruptions.
During public comment, residents asked about drainage and whether curb and gutter would be included across the project; Carter said a few culverts are planned and that future segments might include curb if funding becomes available. The board moved and approved the contract on the record.