Council tables Curio change order for 2700 West lift station, city attorney warns of liquidated damages
Summary
West Haven council tabled a contractor request to extend the completion date for the 2700 West lift station after the city attorney recommended conditions including weekly inspections, emails to the project engineer and continued staff attendance at update meetings; the motion passed unanimously.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
The West Haven City Council voted to table change order number four from Curio Incorporated, which sought an extension of the completion date for the 2700 West lift station.
City Attorney Amy recommended that the council table the request and impose conditions before further consideration. Amy asked that Curio conduct weekly site inspections and email Gardner Engineering so the engineer can forward those reports to the council; she also recommended that either Brian or Russ continue to attend the weekly Zoom update meetings with Gardner Engineering. Amy reminded the council that liquidated damages remained a potential penalty if the contractor failed to reach substantial completion by June 5 or final completion by June 19.
A council member moved to table the change order, another member seconded, and the motion passed on a roll call with all voting in the affirmative.
The tabling leaves the change order unresolved; the council instructed staff to ensure Curio follows the weekly inspection and reporting steps and to return the item for future consideration. Council members also asked that Curio appear at the July 20 meeting to report on progress.
The action leaves the schedule and potential liquidated-damages exposure in place pending further documentation from the contractor and updates from Gardner Engineering.