Middlefield building committee approves contractor payments and change orders for firehouse project
Summary
The Middlefield Public Safety and Firehouse Building Committee on March 18 approved payment to IGS, several change events including a pipe-spec substitution and a screen wall allowance, and a $175 administrative invoice while noting construction schedule challenges.
Get email alerts on the Construction Project Management topic
No spam. Unsubscribe anytime.
The Middlefield Public Safety and Firehouse Building Committee voted March 18 to approve contractor payments and several change events tied to the town's firehouse construction project, and members discussed schedule challenges with the design-build team.
Paul Pizzo, chairman of the Middlefield Public Safety and Firehouse Building Committee, opened the meeting at 7:05 p.m. and led routine business including agenda and minutes approval. The committee then reviewed construction progress and pay applications.
Committee members approved payment to IGS for Invoice #21334 ($2,810.13) and Invoice #21335 ($750.00), for a combined total of $3,560.13. Kevin Boyle made the motion to approve the payment; Steven Tyc seconded and the motion carried.
The committee also approved change event #0016 to revise the underground piping specification from CI to SCH#80 PVC (the record states the change produces an undetermined credit amount; no dollar value was provided). Kevin Boyle moved the change; Bruce Villwock seconded and the motion carried.
An administrative invoice for $175.00 from Amity Wilson for FBC administrative services (submitted for February 2026) was approved on a motion by Paul Pizzo, seconded by Bruce Villwock. The minutes were signed "Respectfully submitted" by Amity French-Wilson.
The committee approved change event #0017.1 (Screen wall, part 1, Rev #1) with a not-to-exceed amount of $10,500.00 after a motion from Steven Tyc and a second from Kevin Boyle.
During the meeting members noted "some challenges" encountered in construction work with the design-build team; the minutes record discussion of schedule and progress but do not list specific schedule changes or deadlines.
The meeting concluded with a motion by Bruce Villwock to adjourn at 8:04 p.m., seconded by Steven Tyc. Motions for each listed payment and change event were recorded as "Motion Carried."