Council approves $23,560 safety platforms and 90‑day extension for wastewater digestors

Carroll City Council · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $23,560.50 change order to add two exterior working platforms to digestors at the wastewater treatment plant for operator safety and valve/pump access, and accepted a 90‑day extension to the contractor’s completion date.

During construction of the wastewater treatment plant digestor and VLR conversion project, staff and the contractor identified a need for two exterior working platforms at the digestors’ access doors to improve operational safety and allow valve and pump maintenance. The proposed cost is $23,560.50 and the contractor requested a 90‑day extension to the contract completion date.

Randy said the platforms are approximately 4 by 8 feet, require custom fabrication and footings, and were not anticipated in the original bid because of changes in the digestor covers and access. Council members pressed why the platforms were not included in the design; staff said the need emerged during construction and the contractor provided a price. Randy said the platforms are required to safely operate valves and pumps that sit about 23 feet below access points.

Council approved the change order to add the platforms and the 90‑day extension on a roll‑call vote, citing operator safety as the primary rationale.