Cochran council hears park project update; revised contract lowers expected costs

Cochran City Council · May 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Manager Richard Newbern reported a redesigned Cochran Community Park project with $1.447 million in committed funding and a revised construction contract reduced to $1,254,336.75 after bid negotiations; a pre-construction conference is scheduled for March 18.

City Manager Richard Newbern presented a detailed update on the Cochran Community Park at the March 11 Cochran City Council meeting, outlining funding sources, contract revisions and schedule steps.

Newbern said the 5.28-acre park land was donated by Earl Arnold in December 2021 and that engineering in July 2022 confirmed the site was not wetlands. He reported total project funding of $1,447,000, comprised of $75,000 from Havenwood Daisy Senior developers, $217,000 from the city's federal ARPA account, and $1,155,000 from the Governor's Office. Newbern said a pre-construction conference is scheduled for Tuesday, March 18 at 10 a.m.

According to the presentation, ICB Construction Group of Macon was the only bidder at an initial $1.931 million; after working with Falcon Design the bid was reduced to $1,439,300 and the revised construction contract is $1,254,336.75, producing total project costs estimated at $1,388,074.53. Newbern said the project was redesigned to fit within budget constraints, removing pickleball courts and fitness stations from the plan.

Newbern also reported that the city will purchase a prefabricated restroom from CXT Incorporated at an estimated $133,737.91, down from an earlier estimate of about $257,000. Engineer James Jones is scheduled to appear at the April 3 work session to discuss pavilion and restroom options.

Why it matters: The revisions narrow the gap between available funding and construction costs and reflect design trade-offs that remove some recreation elements to stay within budget. Final contract documents and pre-construction steps will determine whether the project proceeds on the reported schedule.

Next steps: Pre-construction conference March 18; design details and pavilion/restroom options to be discussed at the April 3 work session.