Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Streets Reconstruction topic

No spam. Unsubscribe anytime.

Council backs $5.625 million Clark Street reconstruction grant application to federal STBG program

Carroll City Council · January 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a resolution committing local funds and operation/maintenance assurances for a proposed $5.625 million full-depth reconstruction of Clark Street, and authorized submission of a $1 million federal STBG application for federal fiscal year 2030; staff said award notices are likely in May.

Carroll City Council voted to commit local funding and to submit a federal Surface Transportation Block Grant (STBG) application to reconstruct Clark Street from near St. Anthony Hospital south to U.S. 30.

City staff presented an estimated total project cost of $5,625,000 and said the city will seek $1,000,000 in federal aid (federal fiscal year 2030) toward that total. The proposed reconstruction would be full depth and include pavement, sewer, water, storm sewer and sidewalks; staff said the project would replace the entry currently in the capital improvement program slated for 2030 if the grant is awarded.

When asked about timing, staff said award decisions are likely in May and that federal funds can be reduced or adjusted by the granting agency. Staff also explained the federal-aid eligibility process—streets are classified jointly with state DOT representatives and only a percentage of mileage is eligible for federal aid.

Council approved a resolution committing funds and assuring future operation and maintenance for the Clark Street reconstruction application. The resolution authorizes staff to file the STBG application by the Jan. 30 deadline and to include the project in the capital improvement plan if the application is successful.

Next steps: Staff will submit the STBG application before Jan. 30 and will report back when funding decisions are announced.