City staff recommend $1.6 million Caterpillar control-system upgrade for Pella's diesel plant
Summary
City staff and the electric director recommended replacing the plant's bespoke control system with a Caterpillar system (approx. $1.6 million) to improve maintainability, reduce contractor reliance and preserve about $1.5 million in reserve-capacity payments; council will consider the contract at a future meeting and installation is expected after summer.
Get email alerts on the Utilities Diesel Plant topic
No spam. Unsubscribe anytime.
City staff and Electric Director Nate Spurgeon told the council that the control system for the city's 28-megawatt diesel-generating plant is aging and presents operational risks and a maintenance burden.
Staff outlined two options: re-engineer the existing third-party bespoke system (estimated about $650,000) or install a universal Caterpillar control system (estimated about $1.6 million). Staff recommended the Caterpillar system, saying it is a more widely supported platform that will reduce future dependence on external contractors and ease operations as long-term employees retire. "There's a Microsoft Windows operating system that operates our $1.5 million annual capacity payments on a Windows PC," Nate said, arguing for the more maintainable, industry-standard platform.
Staff noted the plant has recently been used to support regional transmission orders and that the city receives reserve-capacity payments from Missouri River Energy Services (about $1.5 million annually), which are contingent on the units being operational. City staff said they expect to include the contract authorization on a forthcoming city council agenda with contractor work likely after the summer.
Council members asked timing and lifecycle questions; staff clarified the recommendation does not include engine overhauls and that engines have an overhaul interval different from the control-system decision. No final contract award was taken at this meeting; the item will return for formal action.