Holt County awards Redbird Bridge rehabilitation contract to Garcia‑Chicoine Enterprises for $151,505

Holt County Board of Supervisors · June 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its June 16 meeting, the Holt County Board opened bids for the Redbird Bridge rehabilitation (Project No. C45(575)) and accepted the low bid from Garcia‑Chicoine Enterprises for $151,505, with a completion date listed as Sept. 6, 2026.

O'NEILL, Neb. — The Holt County Board opened bids on June 16 for the Redbird Bridge Rehabilitation Project No. C45(575) and accepted the low bid from Garcia‑Chicoine Enterprises.

Bids opened at 11:30 A.M. were: Garcia‑Chicoine Enterprises, $151,505.00 (completion listed Sept. 6, 2026); JMN Construction, $190,532.00 (completion Dec. 2026); and Nemaha Infrastructure, $222,648.20 (60 calendar days). Bowman representative Gregory Hutmacher reviewed the bid documents for the Board.

On a motion by Supervisor Breiner and second by Supervisor Tielke, the Board voted to accept the low bid from Garcia‑Chicoine Enterprises for $151,505.00. Voting aye were Linquist, Neiman, Frahm, Tielke, Breiner and Paxton; Supervisor Josh Treptow was absent. The motion carried.

Why it matters: The contract award starts the procurement and scheduling process for a local bridge rehabilitation project, with a low-bid contractor and a completion date the bidder listed. The minutes record the bid amounts, the review by Bowman's representative, and the Board's acceptance of the low bid.

The Board adjourned at 12:15 P.M.; the minutes show the contract award as a formal action recorded in the June 16 meeting.

Provenance: Holt County minutes, SEG 014–SEG 015.