Perry DPW reports generator gas-line repairs pending, lagoon mixer project completed
Summary
Superintendent Kevin Tyler told council the city is waiting on gas-line repairs for a generator, is awaiting EGLE response to a corrosion plan, completed the lagoon mixer project, and finished a Vactor part install with auction to be discussed later.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Kevin Tyler, superintendent of public works, updated council on several operations: repairs to the generator gas line remain pending; water-quality samples are being taken; a corrosion-control plan has been submitted to EGLE and the city is awaiting a response; and the lagoon mixer project is complete.
Tyler also reported that a Vactor part install is complete and said he will bring a proposal to send the machine to auction at a future meeting. No formal council action on DPW capital projects or contracts was recorded at the April 3 meeting.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.