Commission approves $500,000 funding plan for assessor/DMV remodel to fix roof, HVAC and plumbing

Kane County Commission · June 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After staff showed evidence of water leaks and aging HVAC, the commission approved moving forward with a remodel of the assessor/DMV building with $200,000 from buildings-and-grounds and $300,000 from the Municipal Building Authority (MBA), including contingency and soft costs.

Kane County commissioners on June 30 approved a $500,000 funding plan to remodel the assessor/DMV building after staff detailed persistent leaks, aging HVAC and a deteriorating roof.

Sheriff Ray and facilities staff described visible water damage, failing floor areas and an HVAC system that is more than 20 years old; facilities said a minimal remodel would likely cost about $200,000 but full remediation with contingencies could push the total higher. “It should be a 1 time cost, and we should be good for another 20 years,” Ray said of the proposed scope.

Staff recommended splitting the cost across budget years and funds: $200,000 from the buildings-and-grounds budget (split across this year and next) and $300,000 from the MBA fund (also across two years). Finance staff said the MBA fund has a multi-million-dollar balance with approximately $2.1 million available after obligations, and recommended the MBA as the primary cushion for the project.

Commissioners discussed contingency assumptions (staff suggested $50,000–$80,000 as a contingency estimate and recommended value engineering in design) and directed the design team to develop options that meet a target budget while addressing known issues (roof, HVAC, plumbing). Commissioner Patty Cabey moved to approve proceeding with the contract and the funding plan; the motion passed on a voice vote.

The county will proceed to finalize designs, incorporate contingency as needed, and return with contract documents; staff said the work is planned to start in the fall and carry into spring to avoid service interruptions.