Development Planning Services Committee approves $14.99 million contract for Horizon South Chamberlain Connector
Summary
The committee approved a negotiated $14,991,088.23 contract with Garick Civil Works to build the Horizon South Chamberlain Connector, funded by SPLOST 2328; staff said the project keeps overall design intent while reducing corridor scope and expects completion in late 2028–early 2029.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The Development Planning Services Committee approved a negotiated $14,991,088.23 contract with Garick Civil Works to construct the Horizon South Chamberlain Connector, committee members heard Tuesday morning.
"This item is a bid contract with Garick Civil Works for the Horizon South Chamberlain Connector project," said Mr. Titus during the presentation, explaining that bids received on March 12 included a lowest offer that was "substantially over budget at 18.2 million." He said staff and the low bidder negotiated value-engineering changes that preserved the overall design intent while narrowing the roadway corridor and produced the lower contract price to be funded from SPLOST 2328.
The committee was told the contract allows 600 days from the notice to proceed for completion. "600 days," said Kyle when asked about schedule, and staff noted a roughly 500-foot bridge crossing the creek will likely be the critical path, with an expected finish of late 2028 to early 2029, weather permitting.
During the meeting a member moved to approve the contract and another seconded the motion; the chair recorded that the motion was moved and the consent action passed as stated on the record. The transcript does not include a roll-call vote tally.
Staff characterized the measure as an important local road project intended to connect Chamberlain Road to Horizon South Parkway via a central roundabout and onward to Gateway Boulevard, and predicted it will help alleviate traffic on Horizon South Parkway, Chamberlain Road and Williams Parkway.
The presentation also included standard informational items (workload monthly reports, a development services monthly report, and a financial report) and a list of temporary alcohol permits tied to local events; no substantive changes or legal matters were reported. With no further business, the committee adjourned at 8:56 a.m.
What happens next: the contract award and construction schedule are set to proceed under the terms described in the meeting; the transcript does not record a detailed vote tally or identify the individual mover and seconder by name.