Two alignment options proposed for Old Telco Road near new commercial development; commission seeks cost responsibility details
Summary
Staff showed two options to realign Old Telco Road at a planned commercial plaza on Highway 34. TxDOT-preferred Option 1 creates a 90-degree approach and longer stacking; Option 2 is a tighter, lower-cost alignment. Commissioners asked who would fund right-of-way and construction and asked staff to confirm developer/city responsibilities before deciding.
Get email alerts on the Road Realignment topic
No spam. Unsubscribe anytime.
The commission reviewed two proposed alignments to connect Old Telco Road to Highway 34 near a planned commercial plaza during the Aug. 17 workshop. Staff said TxDOT favors a connector that provides a 90-degree approach to Highway 34 with more stacking room for turning vehicles (preferred Option 1); the alternate option keeps Old Telco on its existing skew with a closer connection but limited stacking.
Staff and commissioners discussed practical effects on a nearby historic residential area (Sonoma Trail/neighboring streets) and how each alternative would create different access patterns for local residents and for drivers accessing the new commercial driveways. Commissioners requested clarity about cost responsibility and asked whether the developer, the Ennis Economic Development Corporation or the city would construct and fund the realignment, noting construction on new street connections can require right-of-way, grading, curb and signal work beyond a single developer driveway.
Staff said they would verify cost expectations and any prior discussions and report back. No alignment decision was made at the workshop; commissioners emphasized the need to avoid creating an unsafe skewed intersection as traffic increases in the corridor.