Grand Ledge DDA: ADA observation platform construction underway; staff flags need for extra funds
Summary
DDA staff reported the ADA observation platform project began Feb. 2 with retaining-wall work nearly finished and decking and concrete piers next; Assistant City Manager Amee King told the board the project has encountered items that will require additional funds, amount not specified.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Grand Ledge Downtown Development Authority on March 11 heard an update on the ADA observation platform project, with Assistant City Manager Amee King saying construction began Feb. 2 and that unexpected items will require additional funding.
King told the board the retaining-wall blocks are nearly complete. She said the next construction steps are the deck, installation of pier footings and the lower concrete slab, followed by the beam and top slab and the stairs.
King reported that “we have encountered several items that will cause additional funds necessary,” but she did not specify a dollar amount. No motion or vote to allocate additional funding was recorded during the meeting.
The board received the update as part of the staff reports; there was no formal action on the project at this meeting.