Board approves $245,167.50 bid to renovate high-school parking lot; adds seal-coat/striping package
Summary
The Frankfort-Elberta board awarded AJ's the base paving/drainage bid of $245,167.50 for a middle/high-school parking-lot expansion and approved a $20,000 district seal-coating and restriping package to blend the new and existing pavement and improve lot appearance, with additional site items to be bid separately.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Frankfort-Elberta Area Schools Board approved a base bid of $245,167.50 to AJ's to expand and renovate the middle/high-school parking lot, including drainage work and new paving, after a post-bid review clarified that elements such as trees, lighting, bus-area reconfiguration and a storage building were not included in the base contract and will be handled as separate procurements.
Administration and the finance committee presented the long-range planning rationale: as the district prepares a 10-year infrastructure plan it must sequence capital projects and match them to financing options (bonds versus general-fund maintenance). The finance report said the bids returned were under worst-case estimates and the recommendation to award AJ's was made to secure contractor scheduling for a midsummer construction window.
Board members discussed scope exclusions and next steps. Several routine site items — tree planting, lighting specification and a possible storage-building pad — were noted as additional work that could be packaged later or rebid as needed. Administration said some follow-up items will require separate approvals once their costs are defined.
At the meeting the board also approved a district-wide seal-coating and restriping contract with Brian Superior Seal Coating at a cost of $20,000. The administration recommended the seal/stripe package to ensure the newly paved and existing surfaces blend visually and functionally, and to capture a modest $650 cost saving by coordinating the work with the renovation.
Votes and implementation: The board approved the AJ's paving bid and the Brian Superior seal-coating contract by roll call; the parking-lot base bid is budgeted under capital/bond planning and some maintenance items will be paid from general-fund capital improvement. Administration will return with specific contract addenda or separate bids for lighting, bus-area paving and the storage-building pad.