East Marshall board considers $19.8 million bond, weighs options for Gilman building
Summary
The East Marshall Community School District outlined a $19.8 million bond proposal to fund facility upgrades, discussed levy changes that could raise the tax-rate question to 4.05 per $1,000, and debated options for the aging Gilman building as the board faces a Sept. 17 petition deadline.
Get email alerts on the School Bond topic
No spam. Unsubscribe anytime.
The East Marshall Community School District board reviewed a proposed $19.8 million bond package and a tight petition timetable during a special meeting. A district staff member told the board the deadline to deliver petition signatures to the county auditor is Sept. 17 and that the board will likely need to finalize bond language at a special meeting before petitions can be circulated.
The presenter said a previously cited levy figure needed correction and discussed possible levy outcomes tied to the bond. ‘‘We’re bumping up against the wall here,’’ the staff member said, urging the board to set scope and messaging quickly so petition circulation can begin. Board members discussed whether to pair bond authorization with a separate levy-authorizing question; the meeting notes and staff analysis said any levy request above the 2.70 threshold will require two ballot questions and a 60% approval rate for each question under current law.
Board members spent substantial time on the future of the Gilman building. One board member summarized options ranging from a basic renovation (roughly $1.4 million in the presenter’s estimate) that would remove some wings and update HVAC and classrooms, to expanded renovations adding community-accessible fitness or multipurpose space that could bring the Gilman portion closer to $2.2 million. An auditorium was discussed as a longer-term possibility but was described in the meeting as outside the present bond scope, with cost estimates discussed in the meeting in the $4.5–$5.5 million range for a new, 600-seat facility.
Members emphasized the importance of clear public communication about what the bond would fund. The board and presenter discussed using short videos and fact-focused messaging to show voters what would be gained for the proposed tax increase and to explain how construction costs and community priorities shaped the proposal.
Board members also flagged academic program needs that factor into facilities planning. Multiple speakers said the district’s CTE (career and technical education) spaces are outdated and that students are choosing to open-enroll elsewhere for superior CTE classrooms and equipment.
Next steps described in the meeting: finalize project scope and bond language at an early special meeting, prepare petitions for circulation after the facilities meeting on Aug. 27, and consider a subsequent resolution in mid- to late September to call for the election if petition thresholds are met. The presenter urged volunteers to help circulate petitions (noting that board members themselves may have restrictions on directly soliciting signatures) and to prepare clear, concise facts to share with the community ahead of any ballot question.