BOMA directs continuation of reservoir raw water transmission line via TVA easement
Summary
City engineers presented plans for a reservoir raw water transmission line using a TVA easement; after board discussion the BOMA directed staff to proceed with the process as planned.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Engineer Will Brasfield presented a plan for a reservoir raw water transmission line proposed to run via an existing TVA easement. Assistant City Administrator Dan Allen supplemented the presentation with project context.
The Board of Mayor and Aldermen discussed the proposal's technical and procedural aspects and directed Brasfield to continue the process as currently planned. No vote was required or taken; staff will proceed with design and permitting steps in accordance with existing processes.
The minutes do not record specific budget figures or a timeline for completion; those details will appear in subsequent project updates or staff reports.