Cochran council awards $1.41 million contract to build North Ash Street park

Cochran City Council · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Cochran City Council unanimously awarded a $1,409,672.12 contract to ICB Construction Inc. to build a 5.2‑acre city park on North Ash Street. Council discussed safety, restrooms and accessibility; the project is within the city’s $1,447,000 park budget and carries a 330‑day contract term.

The Cochran City Council unanimously voted Dec. 10 to award a $1,409,672.12 construction contract to ICB Construction Inc. for a 5.2‑acre city park on North Ash Street.

City Manager Richard Newbern and council members discussed the project during the meeting; council members noted the bid is within the city’s approved park budget of $1,447,000 and that the contract establishes a 330‑day timeline for Phase 1 construction. Council Member Shane Savant moved to award the contract; Council Member Carla Coley seconded the motion, which carried unanimously.

Council discussion emphasized public‑safety features, including lighting and cameras, and raised questions about restroom facilities and accessibility accommodations for the new park. The council did not specify a construction start date at the meeting; staff were directed to proceed with standard contract execution and mobilization steps.

The award commits the city to a multi‑hundred‑thousand‑dollar capital project funded from the park budget; further design and procurement details, and any required change orders, will be handled by staff under the approved contract authority.

The council’s action follows earlier planning and budget approvals for the park; residents may expect updates from City Hall as construction scheduling and contractor mobilization are finalized.