Summary
Council authorized staff to proceed with rehabilitation of the beach restroom building, prioritizing plumbing repairs to stop water loss and making a plan to split work (plumbing, HVAC, roof) to stay within procurement thresholds and meet a pre-summer completion target.
Get email alerts on the Public Facility topic
No spam. Unsubscribe anytime.
City staff and consultants presented a plan to rehabilitate the beach restroom building, identifying major needs: plumbing repairs to stop ongoing water loss, improved HVAC/ventilation to reduce condensation and mold risk, and a roof replacement. Staff identified options to split the work into separate contracts so that individual components would fall under procurement thresholds and allow work to proceed more quickly.
Rachel (parks staff) said plumbing is the most urgent need because ongoing leaks have required the building to remain in partial or full operation limitation; Fairburns and other contractors had inspected the building and proposed repiping that would avoid future excavation through concrete pads. Council members asked whether the work would require digging into the slab; staff said the plan is to cut out the inaccessible line and reconfigure piping to avoid repeated concrete work.
Council discussed budget and timing: the capital-improvement plan included funding for the rehabilitation (council cited a budget figure of $80,000, with packeted estimates at roughly $52,250 so far, omitting painting and carpentry). Staff said they expected to complete the essential plumbing and HVAC work before summer and would return bids/quotes for items above city policy thresholds.
Council approved a motion authorizing staff to proceed with the rehabilitation approach described—staff will secure quotes, verify permits, and bring back any items whose bids exceed policy limits for council review.