Council approves sewer computer and multiple pump replacements after power surge

Bloomingdale Village Council · March 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Bloomingdale council authorized replacement of a failed sewer plant computer (~$16,966), an east pond pump (up to $12,000), a new effluent pump (up to $15,000), a south lift station pump (up to $8,000) and a one-time west pond weed treatment ($3,700). All motions carried.

Council members approved a series of measures on March 17 to restore and protect the village sewer system after equipment failures attributed to a recent power surge and winter conditions.

The council authorized purchase and installation of a new sewer plant computer, software updates, data restoration and staff training at an estimated cost of approximately $16,966. The minutes record a motion to proceed moved by G. Simpson and supported by R. Empson; roll call was affirmative and the motion carried.

Separately, the council approved replacements for several pumps: an east pond pump damaged by the surge (cost not to exceed $12,000), a new effluent pump to restore the system to two operational pumps (cost not to exceed $15,000), and a south lift station pump damaged during a power outage (cost not to exceed $8,000). Each action was approved by motion with recorded support and "Roll-Yes. Motion Carried."

The council also approved a one-time west pond weed treatment under the existing permit at an estimated cost of $3,700. For ongoing issues with two auto samplers that have frozen in winter conditions, the council agreed to contact the manufacturer for service and troubleshooting; no procurement action was taken on samplers at this meeting.

The minutes record these actions as approved expenditures; they do not specify vendor names, warranty or expected lead times. The minutes do not include line-item budget reallocation language, so implementation is presumed to follow standard purchasing and accounting processes recorded by staff.