Easton conservation panel approves Maple Road house, requires extra silt protections
Summary
The Conservation Commission approved application #26-737 for a new house at 290 Maple Road on March 24, 2026, adding a stipulation that hay bales or a double silt fence be used to protect nearby wetlands.
Get email alerts on the Maple Road 26 737 topic
No spam. Unsubscribe anytime.
The Easton Conservation Commission approved application #26-737 (290 Maple Road) at its March 24 special meeting, adding a site-specific stipulation requiring hay bales or a double silt fence to protect adjacent wetlands.
Joseph Paoleti of Gold Lane Builders appeared for the owner and said the owner wanted plan approval for appraisal purposes. Commissioners who performed a site walk asked how many trees would be removed and expressed concern about preventing silt and erosion from entering a nearby stream. Paoleti said the contractor will use hay bales and silt fencing as proposed.
Cathy Alfandre moved to approve #26-737 with the standard stipulations and the additional sediment-control stipulation; Kevin Kilner seconded the motion. The motion passed by unanimous voice vote.
Commissioners asked staff to ensure wetland flags are installed once snowcover melts and to review tree‑removal plans if further clearing is proposed.