North Fond du Lac board awards Polk Street improvements contract to Advance Construction for $944,177.05
Summary
The Village of North Fond du Lac Board of Trustees voted 5-0 to award the Polk Street Improvements Project to Advance Construction Inc., accepting the low bid of $944,177.05 after a bid tabulation of eight offers was presented.
Get email alerts on the Polk Street Improvements topic
No spam. Unsubscribe anytime.
The Village of North Fond du Lac Board of Trustees voted 5–0 on Jan. 5 to award the Polk Street Improvements Project contract to Advance Construction Inc. for $944,177.05.
Director of Public Works Mitch Vis presented a bid tabulation showing eight bids for the Polk Street project and recommended awarding the work to the lowest bidder, Advance Construction Inc., at $944,177.05. Trustee Gary Schaub moved to award the contract as recommended; Trustee Mike Will seconded and the motion carried with five ayes.
The board did not record additional conditions or amendments in the minutes; Director Vis made the recommendation based on the bid tabulation. The contract award authorizes staff to proceed with standard procurement follow-up and project scheduling for the Polk Street Improvements Project.