Three Oaks council approves change order and two contractor payments for lagoon work
Summary
Council unanimously approved Change Order #6 ($63,410) and two contractor payments — draw #6 ($194,974.20) and Oselka payment #6 ($187,500) — to continue work on the lagoon and associated infrastructure.
Get email alerts on the Infrastructure Payments topic
No spam. Unsubscribe anytime.
The Three Oaks Village Council approved a set of construction payments tied to the lagoon lift-station and related infrastructure during its Aug. 13 meeting.
Council approved Change Order #6 for $63,410 to connect into the existing force main and repair a cracked 18-inch gravity pipe near the Lagoon Lift Station. The motion was moved by Hinman, supported by Jones, and carried unanimously.
The council also approved draw #6, a payment of $194,974.20, on a motion by Jones supported by Hinman, and Oselka payment #6 for $187,500 on a motion by Thomas supported by Springer; both motions passed unanimously. The minutes record full council support for each action.
Council did not add conditions to the payments during the meeting and did not discuss withholding funds; the actions were recorded as approvals to continue and pay for ongoing construction work.