Redevelopment authority approves change order for lighting work, OKs roundabout payment
Summary
The commission approved Change Order No. 9 to address an electrical service connection for a Colorado tracking project and authorized payment for roundabout construction work (payment discussed at $253,350); staff said the overall project remains under budget.
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
The Hobart City Redevelopment Authority approved a contract change order and authorized a roundabout payment at its March 16 meeting.
Staff explained that Change Order No. 9 covers work to reach the electrical junction box after a utility pole relocation, requiring a directional bore and associated work to complete lighting and related systems. The presenter said the project remains about $64,000 under budget even after the change order and recommended approval. The commission moved, seconded and approved the change order by voice vote.
Commissioners also reviewed payment #1 for the roundabout project; staff said most major work is complete though minor items remain. The payment amount was discussed in the meeting as $253,350; a motion to approve the payment was seconded and approved by voice vote.
Staff noted there are additional potential change orders pending while negotiations with utilities and contractors continue; the presenter said pending items may further reduce the project cost because allowances may be adjusted during negotiations.