Three Oaks water projects advance; lagoon nearly complete with 10% payment holdback discussed

Village of Three Oaks Public Service Committee (PSC) · January 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told the Public Service Committee that the Hickory Street valve and water main project will be bid soon, the lagoon project is mostly completed with a recommended 10% retention on final payment to cover defects, and a generator replacement has been ordered; valve mapping and Well #4 evaluation are planned.

Village public works staff updated the Public Service Committee on ongoing water and sewer work and near-term capital projects.

Staff said the Hickory Street valve and water main replacement project will be advertised for bids shortly and that a local contractor, Oselka, has expressed interest in bidding. Staff also reported that security improvements at the water plant — including rekeying doors — are complete and that additional LED lighting quotes are being obtained.

Staff discussed several operational upgrades tied to the AT&T copper-line phase-out, including plans to convert alarms to cellular service. Well #4 will be evaluated in the spring; staff said valve mapping is incomplete and that spring cleanup will include a mapping update.

On the lagoon project, staff reported the work is mostly completed but recommended holding back 10% of the final payment (as permitted by contract) to cover potential defects, citing driveway damage the contractor allegedly caused during the project and a recent heavy rain event on Dec. 28 that triggered pump activation and overflow management. Staff also noted a generator replacement has been ordered and is expected to arrive soon.

The committee reviewed these updates but did not take a formal vote on project acceptance or final payments during the meeting; staff will follow up with contract administration steps as needed.