Algood awards $1.52M contract for Buck Mountain tank and booster-pump upgrades; seeks larger county contribution

Algood City Council · December 10, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Algood council voted to award the Buck Mountain water tank and booster-pump construction contract to WO Construction (low bidder) with a contract price discussed at about $1.517 million after change orders; Putnam County is being asked to increase its contribution from $500,000 to $800,000, with the city responsible for the balance.

The Algood City Council voted to award construction of a replacement tank and booster-pump station on Buck Mountain to WO Construction, the low bidder, and discussed change orders that reduced the contract price from an initial $1,638,000 bid to an adjusted figure discussed in the meeting of approximately $1,517,000.

Mr. Morrison told the council WO Construction’s original low bid was about $1,638,000 and that the contractor offered a $110,000 deduction if the council eliminated an additional interior coating inside the tank and a further modest saving by changing the exterior finish from brick to split-face block. The county has agreed to consider increasing its prior commitment (originally $500,000) to $800,000; if the county does not increase its share the city would pick up more of the total project cost.

Mr. Morrison framed the project as a capacity and reliability need: the system currently pumps roughly 115,000 gallons a day on the mountain and the pumps are running about 22 hours a day, which places strain on the aging infrastructure. Council discussion addressed contingency, cost-sharing with Putnam County and whether to make the award contingent on final county funding; legal counsel and staff recommended awarding to the low bidder and accepting the negotiated change order.

A motion to award the contract and accept the change order carried in the meeting record; affirmative votes were recorded from Miss Walker, Councilman Williams, Councilwoman Hawkins and Vice Mayor Hill. Council instructed staff to coordinate final contract documents and to continue negotiations with Putnam County on funding allocation.