Board declines Polk Street storm-improvement bid; to rebid for 2026 construction
Summary
Trustees voted not to award a single, high bid for Polk Street storm improvements and directed staff to rebid in winter for construction in summer 2026, citing a bid that exceeded the engineer's estimate and a compressed timeline.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
The Village Board voted May 5 not to award the Polk Street storm-improvement contract after receiving only one bid that exceeded the engineer's estimate.
Director of Public Works Mitch Vis told the board the lone bid was higher than expected and tied the result to a short bidding timeline; he recommended not awarding the contract. Trustees voted to reject the single bid and rebid the project in the winter for construction in summer 2026. The motion to not award was offered by President Mike Streetar and seconded by Trustee Gary Schaub and passed unanimously.