City reports Anderson Street contract award, federal grant for Grand Avenue trail and airport runway timing
Summary
Staff reported awarding the Anderson Street project to Eastern Rock Concrete (bid ~20.8% under estimate), outlined a Transportation Alternatives Program trail on Grand Avenue scheduled for DOT letting in March, and said an airport runway overlay is on track for early summer pending asphalt availability.
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
At the March 1 PMD meeting staff provided several infrastructure updates.
Anderson Street: Staff said the Anderson Street project was awarded to Eastern Rock Concrete; the low bid came in about 20.8% below the engineer's estimate. Staff said preconstruction steps are underway and contractors could begin work as soon as March, weather permitting; the work will be phased so subsequent construction continues the following year.
Grand Avenue trail: The city received a Transportation Alternatives Program (TAP) grant to construct a 10‑foot concrete multi‑use trail on the west side of Grand Avenue, tying into an existing multi‑use trail near the middle school. Staff noted the grant covers a large federal share, citing project notes that list either an 80/20 or an 85/15 split for federal versus local shares; the project was placed on the March DOT letting with a late start date of July 20 and 20 working days to complete.
Airport runway: Airport committee members said contractor coordination and permitting are complete and that a runway overlay could occur as early as June pending asphalt plant scheduling and preconstruction work.
Why it matters: The Anderson Street contract advances a locally funded street project; the TAP grant will bring federal funds to expand pedestrian/bike infrastructure and connect neighborhoods to schools and parks; the runway overlay preserves airport infrastructure and supports local air service.
Next steps: Staff will complete preconstruction tasks and coordinate DOT letting for the trail; the Anderson Street contractor will mobilize when preconstruction is complete; staff will monitor scheduling and weather for the runway overlay.