Council approves $72,676 change order to add work on airport runway apron

Manchester City Council · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 1 for additional milling, overlay and pavement markings at the airport apron and taxi area totaling $72,676.30, with the city’s 5% share of the addition cited as $3,633.82 and remaining within budgeted local match.

Manchester city councilors approved a change order adding work to the airport runway and apron project, including milling/overlay and pavement markings near the fuel pump and taxiway tie-downs.

Staff explained that bids on the runway block came in below expectations, allowing additional scope to be added. The total proposed change order was $72,676.30, with the city responsible for 5% of that additional cost (reported as $3,633.82). Staff said the city’s share with the change order remains below the previously budgeted local match for the larger project.

Council discussed the scope (which staff characterized as maintenance, not an expansion of the paved area), asked clarifying questions about the age of the existing apron, and approved Resolution 19 to accept the change order.