Fire, roads and transfer-station operations discussed as Lebanon sets budget and procurement plans

Town of Lebanon Select Board · June 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Department heads briefed the Select Board on fire/EMS staffing and a proposed fee schedule, road paving priorities (Long Swamp, Little River, Center Road), and transfer-station operations; the board discussed hiring, RFPs for a new truck, and bridge safety issues.

Department heads used the June 30 meeting to update the Select Board on several operational priorities ahead of the new fiscal year.

The fire/EMS chief reported the year finished under budget, payroll is in order, and the department is awaiting a DEA response for a narcotics license needed for controlled-supply handling. The chief circulated a proposed fee schedule and a staffing matrix for events and said the package will include contract language and procedures for apparatus hourly rates and cost recovery. "The fee schedule that I gave to the board was a pretty run-of-the-mill number-wise...but again, I emailed that to everybody today," the chief said; board members asked staff to review the packet before implementation.

Public-works staff gave a paving update: Long Swamp Road work is nearly finished and crews plan to move to Little River Road and then Center Road, with much of the capital paving budget consumed by large-scale patchwork and isolated repairs. Estimates cited during the discussion ranged from roughly $100,000 to $161,000 for larger paving work; staff said they will produce a clean number for budgeting.

The board also discussed a deteriorated bridge near Little River, reviewing whether the town owns the structure and whether it should be decommissioned or removed for safety. Members said the bridge is unsafe for vehicle traffic, currently has Jersey barriers in place, and recommended researching ownership before spending on repairs.

Other operational topics included: preparing for a new pumper tanker and station two clean-out and minor build-out to house Engine 2; plans to draft and review an RFP for a new truck and upfit; transfer-station cleanup, scale and compactor procurement logistics; and review of winter-contract terms and GPS tracking for contractors.

The board scheduled follow-ups: staff to compile solid cost estimates for paving and equipment upfits, to complete background checks and onboarding for new hires, and to pursue legal review on capital-fund carry-forward language discussed during the meeting.

Quotations used in this article are taken from the meeting record and attributed to department heads or board members as recorded in the transcript.